Set-up Pre-Qualification
Home → Contractors → Click PreQual (button)
Tick the boxes in the Pre-qualification list that you require the Contractor to provide.
Notes:
We recommend that you tick the following:
-
Evidence Required - This prompts the Contractor to upload a copy of the item.
-
Review - So you can keep a record of who reviewed each item provided by the contractor.
Evidence Required - This prompts the Contractor to upload a copy of the item.
Review - So you can keep a record of who reviewed each item provided by the contractor.
The default requirements are copied from your template. You can change the defaults by clicking on "Edit Template".
Requesting PreQual Items from Contractors
You have 2 options for requesting Qualification information from your contractors:
-
Wait until the Contractor is assigned to a Job, then use the Job Check List to collect the Pre-Qual items (Usually in the App or via the Email link).
-
Request the information before they are assigned to a job.
To do this Click on the "Send Email Now" button.
Home → Contractors → Pre-Qual
Scroll down to Notification Options in the Manage section
You also have the option to automatically remind contractors when their items are due to expire, either 7 or 28 days before expiry.
Just tick the appropriate box.
Reviewing PreQual Items
After a Contractor has supplied their information, a review request is automatically sent out. Contractors ready for review will have an icon signalling that a review is required.
Your staff can review the items provided by the Contractor.
Click on PreQual to open the page and review the information provided by the Contractor.
Under the ABN view you can see the business details.
By clicking on the blue "Lookup ABN" button the system will confirm the ABN number and autocomplete the Registered Name for the business.
Click Save
If this is not correct you can Reject the Pre-Qual and leave notes of this.
See Pre-Qual Item - Rejection (Below)
PreQual Item - Approval
After the Subcontractor has provided their Pre-Qual information, you can review then Approve, or Reject information provided.
SiteBook records the review status for future reference.
PreQual Item - Rejection
You can Reject the Prequal and leave a note/reason for this.
Example: Invalid ABN
If an item is rejected, you can notify the Contractor by sending another email notification.
The contractor will see the warning when they click on the email link.