Understanding Task Predecessors: | SiteBook Help Center
Understanding Task Predecessors:
Task Predecessors: The 5 Key Types Explained
Updated over 2 months ago Table of contents1. Start to Start (SS)
**Task B can only start after Task A has started.**
Example: Carpentry Labour (Task A) must start before Windows Install (Task B) can start.
2. Finish to Finish (FF)
**Task B can only finish after Task A is finished.**
Example: Waterproofing (Task A) must finish before Tiling (Task B) can finish.
3. Start to Finish (SF)
**Task B can only finish after Task A has started.**
Example: Remove Scaffolding (Task B) can only finish after the Roof Install (Task A) has started.
4. Lag - Finish to Start (-1)
**Task B can start 1 time unit before Task A is finished.**
Example: Trench Inspection (Task B) can start 1 day before Slab Pour (Task A) is completely finished.
5. Lag - Finish to Start (+1)
**Task B can only start 1 time unit after Task A is finished.**
Example: Carpentry Labour (Task B) can start 1 Day after Timber Delivery (Task A) is finished.